This case study is presented by Neset Kutlug, Process Administrator at Greenpeace Mediterranean.
Organization Profile
Greenpeace Mediterranean is based on the
principle that nature knows no frontiers and
neither does the pollution that threatens it.
With main offices located in Malta, Greenpeace
Mediterranean also actively campaigns from
Egypt, Israel, Lebanon, and Turkey to conduct
campaigns throughout the region.
Challenge
The team at Greenpeace Mediterranean needed
a
detailed time plan and well
defined task
management for better campaign coordination.
Until now, all campaigns and initiatives were
being tracked manually, using basic to-do and
follow-up lists. This resulted in a less optimal
use of human resources, especially when
running multiple campaigns at the same time.
"In some of our complex campaign initiatives,
manual task management and follow-up
created time and resource conflicts, thus
jeopardizing the success of those initiatives."
says Neset Kutlug, Process Administrator at
Greenpeace Mediterranean.
Solution
Ease of use, rapid tech support and important
features such as task dependencies were the
deciding factors in finding and evaluating the
right software solution.
"We closely examined three other applications
before arriving at our decision to choose Easy
Projects .NET" says Neset. "The application
offers many complex features yet it is able to
provide a
very user friendly interface and
easy to follow workflow structure."
Easy Projects .NET was chosen as the most
complete project management application as
it could deliver features other solutions could
not adequately provide within the set budget.
Implementation
Easy Projects .NET was first deployed in a small
scale pilot project, to measure how it would
adapt within the organizational culture and
work-flow.
This pilot project ran for just over a month, and
immediately highlighted a number of internal
campaign management aspects which required
immediate improvement.
Following the successful implementation of the
pilot project,
Easy Projects .NET is now used to
manage numerous phases of a large scale,
multinational projects run by Greenpeace
International.
Outcome
Upon deployment, Easy Projects
.NET was immediately perceived
as tool which allows for a
very
organized, effective and
focused way to manage projects.
During the past few months, Easy Projects .NET
has been utilized as a platform to share
information and extensive feedback while
managing campaign tasks.
"Starting in October 2009, we set up two very
critical projects to be managed through Easy
Projects .NET" says Neset. "The shorter of the
two was
successfully completed on
schedule, and taught us a number of very
important lessons concerning our campaign
management and the every-day utilization of
project management software."
The second project in the system is slated to be
completed in April 2010, and continues to be
closely tracked and managed every day through
Easy Projects .NET. "As of January 2010, we will
be completely managing all of our
campaigning activities through Easy
Projects .NET" adds Neset.
Download PDF version of this Case Study